Brief Description and Objectives of the Project
Construction of water supply network, irrigation and wastewater transfer of Barkat pharmaceutical industrial town including:
Construction of water supply and irrigation lines with a cumulative length of 42,000 meters
Construction of sewage transmission lines with a cumulative length of 14,000 meters
Two underground concrete tanks, each with a volume of 5,000 cubic meters
An earthen pool (lagoon), with a volume of 30,000 cubic meters
One air steel tank with a volume of 120 cubic meters, to supply drinking water